Overview of the work completed
Our designers AECOM proposed a solution consisting of a variety of rock fall protection measures:
- The steeper sections of the cutting would be secured with a combination of rock fall netting and rock bolts.
- A series of low and high capacity rock fall fences would protect the track from the shallower rock and soil slopes.
The wide cess area provided an opportunity to utilise specialist plant to install anchor bars for the catch fences, which could operate safely behind a safety fence during normal day time hours. The movement restricted plant, operated under the guidance of the site specific ALO Plan (Any Line Open), eliminated the need for mid-week night time working, and reduced the number of possessions required to complete the works.
Our multi-skilled in-house rope access teams completed all vegetation clearance, rock scaling operations, drilling works, and the installation of nearly 4000 square metres of rock netting.