Farnley Haugh Landslide Repair

Civil Engineering, Earthworks & Drainage

Brief Description

The 25m deep cutting slope at Farnley Haugh suffered a significant failure resulting in the closure of the Newcastle to Carlisle Line, between Hexham and Prudhoe. Over 70,000 tonnes of slip material would end up having to be removed from the cutting to stabilise the slope.

Overview of work completed

The 25 m deep cutting slope at Farnley Haugh suffered a significant failure resulting in the closure of the Newcastle to Carlisle Line, between Hexham and Prudhoe. The site itself is located between Corbridge and Riding Mill, about 7 km east of Hexham, on the Down side (south side) of the Newcastle to Carlisle Line. The line was re-opened to traffic on 8 February 2016.

Network Rail’s archives indicate that the cutting was originally excavated between 1959 and 1962 to replace Farnley Tunnel. The original slope was a cutting with a series of two or three benches,
each with a filter drain. The ground conditions at the site comprise Glacial Sands and Gravels, underlain by the Carboniferous Stainmore Formation (Sandstones, Siltstones and Limestones). Above the cutting is a 2 m wide ditch, which discharges via a headwall and piped drainage system installed on the slope and continues beneath the railway into the River Tyne.

Network Rail Geotechnical Engineers and CML attended site within a few hours of the incident being reported in order to start understanding the scale of the slip and planning the recovery. At that stage it was evident that there was cracking in the field above the slip with fallen trees in the upper and middle parts of the slope and debris on the railway line including trees and wet sandy material. As the slope was still moving, an exclusion zone was formed around the toe, crest and body of the slip.

Overview of work completed

The 25 m deep cutting slope at Farnley Haugh suffered a significant failure resulting in the closure of the Newcastle to Carlisle Line, between Hexham and Prudhoe. The site itself is located between Corbridge and Riding Mill, about 7 km east of Hexham, on the Down side (south side) of the Newcastle to Carlisle Line. The line was re-opened to traffic 4 weeks later.

Network Rail’s archives indicate that the cutting was originally excavated between 1959 and 1962 to replace Farnley Tunnel. The original slope was a cutting with a series of two or three benches,
each with a filter drain. The ground conditions at the site comprise Glacial Sands and Gravels, underlain by the Carboniferous Stainmore Formation (Sandstones, Siltstones and Limestones). Above the cutting is a 2 m wide ditch, which discharges via a headwall and piped drainage system installed on the slope and continues beneath the railway into the River Tyne.

Network Rail Geotechnical Engineers and CML attended site on within a few hours of the incident being reported in order to start understanding the scale of the slip and planning the recovery. At that stage it was evident that there was cracking in the field above the slip with fallen trees in the upper and middle parts of the slope and debris on the railway line including trees and wet sandy material. As the slope was still moving, an exclusion zone was formed around the toe, crest and body of the slip.

The following morning the cracking in the field had developed into a 5 metre high back scar exposing a damaged 300 mm diameter combined sewer. Northumbrian Water later confirmed that it was pumping sewage into the failure at a rate of 400 litres per minute and continued to do so until they were able to put a diversion in place the following day. The event occurred following a prolonged period of heavy rainfall over the Christmas period, which was reported to be the most exceptional period of rainfall on record for the area, with significant overland flows breaching the existing drainage network. Combined with the fractured sewer, this made the cutting slopes an extremely dangerous environment.

For the first four days following the line closure, earthflows were occurring every few hours releasing large volumes of spoil and slurry down towards the railway, amongst the sound of trees snapping like match sticks. This made the hill-side an extremely dangerous place to be, and was simply unsafe to start work until we could control the water and slow down the slope failures. An aerial survey of the failed section was undertaken using an unmanned Aerial Vehicle (UAV), from which a 3D topographical model was derived and used by AECOM in the analysis of the failure. Initial remedial works involved diverting the ditch discharging water onto the slope to an alternative discharge point further along the crest and ensuring that the pumped sewer was diverted. Following the diversion of the crest ditch, work commenced on removing the fallen trees from the slope and track before removal of the failed material itself. Removal of the failed mass was undertaken from the crest down.

The work was further complicated by the presence of a protected Monument comprising the footprints of three Roman camps, the nearest of which is only 15 metres from the crest of the landslide. Working closely with Historic England the various features were mapped out using geophysical surveys before carefully stripping the soil in layers under a watching brief by the Archaeologists. This helped us progress speedily into the crest of the cutting with earth moving machinery to advance remedial works without disturbing the known historic monuments. The survey work undertaken helped contribute to Historic England’s records of the protected site.

From the initial assessment of the causes of the failure, site constraints and possible solutions, we were able to start work re-profiling the slope, combined with a new deep drainage system. The size and steepness of the slope posed a serious challenge for the earthmoving fleet. The challenge was to safely remove 35,000 cubic metres of debris from the cutting slope, minimising disruption to the adjacent stable slopes, and using methods which would be quick enough to ensure we could re-open the railway as quickly and safely as possible. We achieved this by removing the debris simultaneously from the top of the cutting, by multiple handling and using a series of benched access roads, and from the base of the cutting by waggons and freight trains. As the reduce dig works progressed, there were significant ground water flows emerging through sand and gravel layers in the cutting slopes which continued to de-stabilise the lower slopes and which made loading away by train difficult with slurry and debris continuing to foul the railway. Therefore the majority of the material was removed via the crest of the cutting with tracked earth moving machinery.

The future stability of the slope was ensured by the excavation of the failed material and construction of a stable slope profile in virgin ground. The potential stability risks arising from both surface water runoff and groundwater within the more permeable layers daylighting in the slope were addressed in the final design with a surface dressing of stone over the whole slope. The ditch at the crest was cleared, re-profiled and lined with concrete canvas to reduce the risk of future water ingress into the cutting. A small bund was also built to stop water overflowing the cutting crest during extremes of rainfall. The headwall at the top of the slope was replaced and the size of the pipe down the cutting slope was increased, sufficient to cope with the anticipated volumes of water coming from the land above.

A series of 3 m deep counterfort drains were installed across the lower slope, combined with 10m deep plati-drains driven horizontally into the cutting slope. The counterforts fed into a new collector drain constructed on the wider bottom bench, which in turn feeds in to a new drainage pipe passing beneath the tracks, ultimately discharging into the River Tyne. A drainage blanket was also installed on the remediated slope face to control surface runoff and to prevent seepages damaging the surface profile. On completion of the remedial works, four inclinometers and two
piezometers were installed in the slope, which are being monitored monthly to confirm the slope’s continued stability.

Successes

  • This was a complicated landslip to fully understand and remediate due to the ground conditions and the unprecedented groundwater levels and resultant seepages, further complicated with the presence of the Roman Fort and the damaged sewer. With close collaboration between all parties, the Client, Network Rail, the Contractor, CML and the Designer, Aecom, a swift and safe operation was undertaken with the most efficient and effective solution adopted.
  • This project has provided some excellent examples of collaboration, working with Northumbrian Water to divert the sewer, Historic England to protect the Roman Fort, Multiple landowners to provide access, National Media (BBC, ITV, MP’s), various departments of Network Rail to organise train movements and track renewals works, and of course the local residents who took a great interest in the project.
  • The excavation generated over 35,000 cubic metres of inert spoil. Cooperating with the local landowners and the Environment Agency, we agreed to place and landscape the spoil in a safe area in the surrounding fields. This diverted a significant volume of material from landfill, and drastically reduced the number of road vehicle movements further reducing the carbon footprint of the  scheme.
  • The landscaping works at the crest also provided the opportunity to improve the drainage arrangement, and further divert surface water flows from the crest of the cutting to provide greater protection to the railway from future flooding events.
Contact us

More Case Studies

Subscribe to our Digital Newsletter

Keep up to date with our latest news, projects and industry developments