Playing our part in the Transpennine Route Upgrade
As part of the wider Transpennine Route Upgrade, our team is continuing work on the Holbeck Depot Upgrade, one of several smaller depot improvements taking place ahead of the main depot refurbishment (Neville Hill). The upgrades will play a vital role in supporting refuelling operations and increasing train capacity across the network.
Delivering Phase 2
Working under RTS Infrastructure, the principal contractor for Network Rail, we are currently nearing completion of Phase 2. This phase includes installation of a new 105,000-litre diesel storage tank, DNO (Distribution Network Operator) power connection, AdBlue tank slab, plant room slab, surface water drainage, and associated ducting and cabling.
One of the recent key milestones on site was the installation of the steel frame for the gull wing canopy. This marked a major visual step forward, giving everyone on site a first look at the impressive scale and form of the completed structure.